Substation Clearances: 765KV
Minimum electrical clearances for outdoor air-insulated substations per NESC Rule 235 and IEEE Std 1427. Includes phase-to-ground, phase-to-phase, fence, roadway and walkway clearances by voltage class.
| voltage class | bil basis kV (kV) | clearance over roadway ft (ft) | clearance over walkway ft (ft) | clearance to fence ft (ft) | min phase ground clearance in (in) | min phase phase clearance in (in) | nesc rule | standard |
|---|---|---|---|---|---|---|---|---|
| 765KV | 2,050 | 37.5 | 31.5 | 15 | 124 | 148 | NESC_235 | IEEE Std 1312 / NESC 2023 |